6 yrs on, Lathikata-Timjor bridge still lying unused

| | SUNDARGARH
  • 0

6 yrs on, Lathikata-Timjor bridge still lying unused

Wednesday, 25 March 2020 | MAlAY RAY | SUNDARGARH

Lathikata-Timjor high level  bridge on the Brahmani river in Lathikata block under Sundargarh district is yet to be functional even after six years of the laying of foundation stone by

Chief Minister Naveen Patnaik. This is, as the approach road to the bridge has not been readied. About  70,000  people under 11 panchayats  are suffering due to this.

Chief  Minister Patnaik had laid foundation stone of the Lathikata-Timjor bridge on January 22, 2014 but the bridge was completed during April 2019. However, the approach road to the bridge has not been readied.

An agreement had been made between contractor Rajalaxmi  Construction and the Rural Development Department for construction of the Lathikata-Timjor bridge and the approach road at an estimated cost of Rs 22,55,076  crore. The agreement  was made for construction of 612 meter length high level bridge  and approach road of 500 meter length in left side and approach road of 800 meter in  right side.  The approach road has not yet  been constructed because land acquisition could not be done.

There are 18 panchayats under Lathikata block.  On one side of Lathikata block there are seven panchayats and on the other, there are 11 panchayats and in between, there is the Brahmani  river.  On one side of Lathikata block, there are Lathikata block office, Tehsil office, market and some other essential offices, on other side of  block, there are Birkera, Tainsor, Garjan,  Bada  Dalki, Birda, Jadakudar, Balanda, Lungei, Jhartarang, Kalunga and Chikatmati panchayat and about 70,000 people of these 11 panchayats are facing severe difficulties because the bridge has not yet functioned due to the problems in construction of the approach road.  While the water level is low in the river, they cross the river through wooden bridge in unsafe condition and when the water level is high, they also use boat to cross the river to reach the other side of river for their work.

“We have not been able to construct the approach road because we were not provided land for construction of approach road of  1,300 meter length as the land acquisition for had not been done.  The concerned authorities have started land acquisition process and we hope the land acquisition will be completed soon and thereafter we will start construction work of approach road," said Supervisor, Rajalaxmi Construction, Amiya  Panda.

“Total 23 plots are required for  1300 meter  length construction of approach road to the bridge. We have already started acquiring land and the construction work of the approach road  will be completed by  May 2020," said  Executive Engineer, Rural Development Department,  Rourkela, Sushil Samantaray.

Sunday Edition

India Battles Volatile and Unpredictable Weather

21 April 2024 | Archana Jyoti | Agenda

An Italian Holiday

21 April 2024 | Pawan Soni | Agenda

JOYFUL GOAN NOSTALGIA IN A BOUTIQUE SETTING

21 April 2024 | RUPALI DEAN | Agenda

Astroturf | Mother symbolises convergence all nature driven energies

21 April 2024 | Bharat Bhushan Padmadeo | Agenda

Celebrate burma’s Thingyan Festival of harvest

21 April 2024 | RUPALI DEAN | Agenda

PF CHANG'S NOW IN GURUGRAM

21 April 2024 | RUPALI DEAN | Agenda