Burla Power House units resume ops

| | BHUBANESWAR
  • 0

Burla Power House units resume ops

Sunday, 23 January 2022 | PNS | BHUBANESWAR

After the Renovation, Modernisation and Up-rating (RMU) works taken up in units 5 and 6 of the Hirakud Power Station, Burla, the commercial operation of the units have begun on November 2 and January 9, respectively.

The units after rendering continuous service for more than 50 years had recently undergone RMU as per the CEA guidelines. Voith Hydro Private Limited (India) had taken up the work since October 2015 with financial implication of Rs 158.77 crore.   

The capacity of both the units has been enhanced from 37.5 MW to 43.65 MW each resulting in addition of 12.3 MW of power to Odisha grid.  Total hydroelectric power generating capacity of Burla Power House has been increased from 275.5 MW to 287.8 MW. The OHPC had already undertaken RMU work of its 1, 2, 3 and 4 units of Burla HEP in phased manner and fed an additional capacity of 40 MW (12x2 + 8x2) into Odisha grid.  Similarly, all the three units of Chiplima are also generating electric power smoothly

State Editions

SP may send Jayant to RS

26 May 2022 | PNS | Lucknow

4 of a family killed in road accident

26 May 2022 | PNS | Lucknow

UP Budget today

26 May 2022 | PNS | Lucknow

Missing minor girl’s body found in field

26 May 2022 | PNS | Lucknow

Sibal files papers for RS seat from UP

26 May 2022 | PNS | Lucknow

Sunday Edition

GyanVapi to set the new course of Indian politics

22 May 2022 | Shivji Sarkar | Agenda

A nursery of military leadership

22 May 2022 | Pioneer | Agenda

Short stories with big messages

22 May 2022 | Navin Upadhyay | Agenda

Never a bystander: Indian Railways in Transition

22 May 2022 | Deepak Jha | Agenda

Regional parties, Hindi & Hindutva

22 May 2022 | Rahul Jayaram | Agenda

Astroturf | Shape your destiny through conscious efforts

22 May 2022 | Bharat Bhushan Padmadeo | Agenda